Project development economics

Solar financing remains equity-heavy: 55% equity vs. 45% debt on average.

Projects that survive are moving faster

84%
expect CAPEX recovery within six years
44%
expect payback within three years
68%
reach COD within two years (2025: 65%)

Faster to build, harder to get there

Successful projects are moving faster — but more projects are falling away before construction.

of projects
84%

are expected to recover CAPEX within six years

with 44% within three years

Revenue certainty starts with yield certainty

Reliance on all three revenue models declined slightly, with merchant exposure falling most (−5 points), consistent with rising price-volatility concerns and a flight toward contracted revenue.